著者
高尾 喜久雄
出版者
一般社団法人日本機械学会
雑誌
交通・物流部門大会講演論文集
巻号頁・発行日
vol.2005, pp.79-82, 2005
被引用文献数
1 1

We have been developing a gauge change train systems for through-operation between Shinkansen lines and conventional lines. The 1^<st> Gauge Changing Train Set (GCT) was completed in 1998 to confirm the basic efficiency of the systems. The GCT was an experimental 3-motor-car electric multiple unit (EMU) train. It was designed to run at a maximum speed of 300km/h on Shinkansen lines, and 130km/h on conventional lines. It works under a catenary voltage of AC25kV, 20kV and DC1500V. It had been tested for basic and endurance performance at high speed. We are now designing the 2^<nd> GCT for developing new gauge-changing bogies. It will be completed and started to test in late 2006.

言及状況

外部データベース (DOI)

Twitter (1 users, 1 posts, 0 favorites)

こんな論文どうですか? 3309 軌間可変試験電車の開発 : 新幹線・在来線直通運転を目指して(OS2 交通・物流システムの高速化と利便性の向上I,一般講演)(高尾 喜久雄),2005 https://t.co/nULTx6iXt4

収集済み URL リスト