Bureau of Sewerage, Tokyo metropolitan goverment has a plan to increase the efficiency of constructing sanitary or combined sewer tunnels to reduce the cost of shield tunneling for sewerage systems. Specifically, segments in sanitary or combined sewer tunnels are shop-applied with secondary linings to eliminate secondary lining work at the site. This paper describes the results of a study to standardize the method of designing segments shop-applied with secondary linings, which are referred to as “secondary-lining-applied segments”.